Construction Updates

CONSTRUCTION UPDATES

LEARN MORE ABOUT THE PROJECT HERE


WEEK OF OCTOBER 16

 

Painting has begun and will continue this week. The front door and west doors have polywall on them, but faculty, staff, students, and families can all gain access as they would on normal business days. Please be mindful of wet paint on the building, and in the entryways.

IMPACT ON PROGRAMMING: NONE ANTICIPATED


WEEK OF OCTOBER 9

Demolition is complete. Power washing begins Tuesday, October 10 in preparation for painting the week of October 16.

IMPACT ON PROGRAMMING: NONE ANTICIPATED


WEEK OF OCTOBER 2

 

Demolition has begun! Our existing banners, and signage has been removed to prepare for the power washing and painting in the coming weeks.

IMPACT ON PROGRAMMING: NONE ANTICIPATED